New Contract Awards

Maggies Cancer Care Centre, Glasgow

Client

Maggie's Centre

Main Contractor

DBCE

Architects OMA / Keppie
Engineers SKM / RJ Tait

Contract Period

48 weeks

Project Value

£2.3 million

Scope of Works

Single storey concrete framed building with a small basement area with interlinking rectangular rooms arranged to form a central courtyard, full internal fit-out to a very high level of finish.

 

 

Liebherr New Headquaters, Bathgate

Client

Liebherr UK

Main Contractor

DBCE

Architect Slorach Wood
Engineer WMA

Contract Period

38 weeks

Project Value

£3 million

Scope of Works

Reduce level dig, vibro piling, steel frame, corus cladding, curtain walling, overhead crane and full internal fit-out of three floors of offices.

 

 

Southern General Hospital, Glasgow

Client

NHS

Main Contractor

Brookfield Construction UK

Architect Boswell, Mitchell & Johnston
Engineer URS

Contract Period

53 weeks

Project Value

£13 million

Scope of Works

Bulk excavation, Sheet Piling, Reinforced Substructure and Four floors of Upper Reinforced Superstructure incorporating Precast Columns covering an area of 21,000m2.

 

 

University of the West of Scotland, Ayr Campus

Client

University of the West of Scotland

Main Contractor

Bovis Lend Lease

Architect RMJM
Engineer Woolgar Hunter

Contract Period

39 weeks

Project Value

£7 million

Scope of Works Bulk excavation of 24,500m3, Concrete Substructure, Single Storey Basement, 3 Storey Post Tensioned Superstructure, 18,000m2 Building Footprint with associated External and Internal Drainage.

 

 

Friarton Recycling Centre, Perth

Client

Perth and Kinross Council

Main Contractor

DBCE

Architect Dalziel Design
Engineer Halcrow

Contract Period

36 weeks

Project Value

£3 million

Scope of Works Extension of recycling depot including New Bulking Shed, Lorry Park, SUDS Pond and Roads Infrastructure.

 

 

Bayhill High School, Inverclyde

Client

Inverclyde Council

Main Contractor

Miller Construction

Architect Archial
Engineer Stuart McTaggart

Contract Period

23 weeks

Project Value

£1.1 million

Scope of Works Superstructure including Precast Columns and Post Tensioned Slabs.

 

 

Notre Dame High School, Inverclyde

Client

Inverclyde Council

Main Contractor

Miller Construction

Architect Dalziel Design
Engineer Halcrow

Contract Period

19 weeks

Project Value

£1.4 million

Scope of Works

Superstructure Precast Columns with Post Tensioned Slabs and Feature Columns.

 

 

Tyne Tunnel Crossing, Newcastle

Client

TT2

Main Contractor

Bouygues

Services Engineer Faber and Maunsell / Aecom
Structural Engineer HPR

Contract Period

30 weeks

Project Value

£3.5 million

Scope of Works North Cut and Cover works to the north side of the tunnel. This new tunnel will be 1,600m long, including 360m under the River Tyne alongside the existing tunnel.

 

 

Sibbald Training Facility, Blackridge

Client

Sibbald Training Ltd

Main Contractor

DBCE

Architect Davis, Nimmo and Stevens
Engineer David R Murray

Contract Period

18 weeks

Project Value

£750,000

Scope of Works The works consist of the construction of a new 400m2 forklift training facility plus the refurbishment of existing premises to form new offices, training rooms, meeting room, welfare area and main reception.

 

 

Head Office: Dunne Group Ltd, Inchmuir Road, Whitehill Industrial Estate, Bathgate, EH48 2EW Phone: +44 (0)1506 657777 Fax: +44 (0)1506 657770
Regional Office: Dunne Group Ltd, 4205 Park Approach, Thorpe Park, Leeds, LS15 8GB Phone: +44 (0)1132 840540 Fax: +44 (0)1132 840541
Regional Office: Dunne Group Ltd, Leigh Commerce Park, Greenfold Way, Leigh, Greater Manchester WN7 3XH Phone: +44 (0)1942 267470 Fax: +44 (0)1942 267471
©2010 Dunne Group Limited All Rights Reserved