Motherwell College, Motherwell

Client

Motherwell College

Main Contractor

Miller Construction

Architect

BDP

Engineer

Struer

Contract Period

20 weeks

Project Value

£900,000

Scope of Works 8 Storey Concrete Frame in School of Residence

 

 

Bangholm Terrace, Edinburgh

Client

Cala Homes

Main Contractor

Cala Homes

Architect

CDA

Engineer

WSP

Contract Period

20 weeks

Project Value

£930,000

Scope of Works 4 Storey Post Tensioned Concrete Frame

 

 

Fountainbridge North, Edinburgh

Client

Grosvenor /AMA

Main Contractor

HBG Construction Ltd

Architect

Oberlander

Engineer

Goodson

Contract Period

42 weeks

Project Value

£10 million

Scope of Works Phase1: 35,000m3 Bulk Excavation and Temporary Works
  Phase2: Underground R.C Car Park for 500 cars with four post tensioned 6-7 storey buildings above the post tensioned podium slab

 

 

Site 19/20 Paradise St , Liverpool

Client

Grosvenor

Main Contractor

Balfour Beatty

Architect

Austin Smith Lord

Engineer

Waterman Group

Contract Period

50 weeks

Project Value

£9 million

Scope of Works Bulk Excavation, Substructure formed using Waterproofed Caltite Concrete, Ground Bearing RC Slab and Retaining Walls, Reinforced Concrete Columns & Post Tensioned Slabs to Superstructure and Insitu Ramp for Mixed Retail & Customer Parking

 

1 | 2 | 3 | 4 | 5 Next

 

Head Office: Dunne Group Ltd, Inchmuir Road, Whitehill Industrial Estate, Bathgate, EH48 2EW Phone: +44 (0)1506 657777 Fax: +44 (0)1506 657770
Regional Office: Dunne Group Ltd, 4205 Park Approach, Thorpe Park, Leeds, LS15 8GB Phone: +44 (0)1132 840540 Fax: +44 (0)1132 840541
©2007 Dunne Group Limited All Rights Reserved